Oceans Gate

Featured Image

Oceans Gate


Phase 1

Commercial

Project Overview

Print Friendly, PDF & Email

We supported Oceansgate in creating Phase One of the site’s new office and industrial space.

The project required us to carry out work on a three-storey office and two single-storey industrial terraces, arranged in parallel rows. The buildings now offer nearly 3,000m² of office and industrial space with provision for up to 21 businesses.

We fitted a PV array to the roof of the office, with an estimated annual generation of 19,616.00kWh and a declared net capacity of 20.00kWh.

With exposed services, the project demanded a high-quality installation which EX2 delivered throughout.

Client:

Plymouth City Council

Main Contractor:

Midas Construction

Consultant Engineer:

AECOM/SDS

Project Budget:

£750,000

Timescale:

20 Weeks

Works Undertaken:

  • Photovoltaics
  • Plug in Car charging
  • Mains Distribution
  • Small Power
  • Lighting and External Lighting
  • Fire & Refuge Alarm
  • Intruder & Access Control
  • LTHW Heating
  • Natural Ventilation
  • Domestic Services