Marine Academy Joint Forces Cadet Centre
Commercial
Project Overview
EX2 undertook the complete electrical and mechanical services for the new Joint Forces Cadet Centre. Over five months, we covered all areas, from mains distribution and lighting controls to fire alarms and ventilation.
It was vital to deliver the works to the MOD’s exacting standards and we ensured they were completed on time and within budget.
Client:
Wessex Reserve Forces' and Cadets' Association
Main Contractor:
Morgan Sindall
Project Budget:
£165,000
Timescale:
5 Months
Works Undertaken:
- Mains Distribution
- Lighting Controls
- Lighting (Internal & External)
- Small Power
- Fire & Intruder Alarm
- Data Network
- Lightning Protection
- LTHW Heating
- Domestic Services
- Ventilation