Project Overview

EX2 carried out the design, supply, installation and commissioning of the electrical and lighting services for the refurbishment of the Laira Rail bridge in Plymouth. Working closely with Philips lighting we developed a scheme that complimented the structure of the bridge.

Containment and electrical services were carefully coordinated with the existing structure and the installation sequence and method carried out to ensure that the works completed in conjunction with the specialist steel work contractor refurbishment works.

  • Client:Plymouth City Council
  • Main Contractor:SWH Civils
  • Project Budget:£150,000
  • Timescale:6 Months
  • Works Undertaken:
    • Electrical Design
    • LED Deck Lighting
    • LED Decorative Lighting
    • Containment
    • Mains Distribution
    • Lighting Controls
    • Data Networking