Project Overview

EX2 carried out the electrical works associated with the refurbishment of existing office accommodation and reception areas. The remaining areas of the building remained occupied during the works as so essential infrastructure upgrade works had to be carried out to minimise disruption to occupants. As part of the works the fire alarm system to the entire site was also replaced after we were able to demonstrate our ability to work within occupied areas with minimal disruption.

  • Client:South Hams District Council
  • Main Contractor:Integral
  • Project Budget:£275,000
  • Timescale:18 Months
  • Works Undertaken:
    • Mains Distribution
    • Lighting Controls
    • Lighting (Internal & External)
    • Data Networking
    • Fire Alarm (Whole Site)
    • Small Power
    • Standby Generator